This module applies only in areas undertaking the trial of the Single Approach to Isolations on 25 kV a.c. infrastructure as set out in the Scope of the Main Standard. Within the trial areas, this standard supersedes all the requirements of NR/L3/ELP/29987. For all areas not involved in that trial, this standard does not apply and the provisions of the most recent issue of NR/L3/ELP/29987 apply instead.
Within the trial areas, this module provides a consistent approach for the planning of the Electrical Safe System of Work (ESSOW) when working on the operational railway with 25 kV a.c. electrification.
This module includes requirements relating to managing electrical risks associated with Live Overhead Line Equipment (OLE), Live pantographs and other roof-mounted electrical equipment on trains.
This module applies to Network Rail personnel and to Network Rail’s contractors working within the trial areas, when working on the operational railway with overhead electrification or when working off the operational railway but where the workpresents the risk of encroaching within 2.75 m of exposed Live parts, including Live pantographs and other roof-mounted electrical equipment on trains.
To provide a consistent approach for working and managing the interfaces between systems and parties, other Railway Group members may, as best practice, apply this module to infrastructure they control within or adjacent to trial areas.
The requirements of this module do not alter the requirements of the Rule Book Module AC (GE/RT8000/AC). Further requirements are contained in the Rule Book module AC (GE/RT8000/AC) and Handbook 16 (GE/RT8000/HB16), and in Network Rail’s Lifesaving Rules.