Introduction
This Instruction details the additional isolation and earthing requirements necessary to carry out the maintenance of O.H.L. feeder switches. These switches are, for the purpose of this document, defined as those switches which are immediately on the O.H.L. side of a C.B.
This Instruction complements but does not modify the instructions contained in the Working Instructions for A.C. Electrified Lines B.R. 29987.
The following abbreviations apply:
E.C.O. Electrical Control Operator
O.H.L. Overhead Line
C.B. Circuit Breaker