NG UKBP/TP 141 PDF

NG UKBP/TP 141 PDF

Name:
NG UKBP/TP 141 PDF

Published Date:
04/01/2015

Status:
[ Active ]

Description:

UK Business Procedure/Transmission Procedures - Authorisation Process for Commissioning, Settings and Design assurance Roles and Assessment Process for Contractor Design Approval Roles and Principal Designer Role

Publisher:
National Grid

Document status:
Active

Format:
Electronic (PDF)

Delivery time:
10 minutes

Delivery time (for Russian version):
200 business days

SKU:

Choose Document Language:
$275.7
Need Help?

PURPOSE AND SCOPE

This procedure defines the process of achieving competency authorisations for Commissioning, Settings and Design Assurance roles for individuals working on National Grid Electricity Transmission Assets to deliver the Capital Plan. (See Appendix A - Authorisation process for Commissioning, Settings and Design Assurance Roles).

This procedure also defines the process for assessment of Contractor Design Approval roles for individuals working on National Grid Electricity Transmission Assets to deliver the Capital Plan. (See Appendix B - Assessment Process for Contractor Design Approval Roles).

The requirements of these roles are detailed in TP106 for commissioning, TP107 for relay settings, TP188 for design disciplines.

This procedure also defines the process for assessment of the Principal Designer role for individuals working on National Grid Electricity Transmission Assets to deliver the Capital Plan. (See Appendix C - Assessment Process for Principal Designer Role).

Principal Designer shall undertake duties in accordance with Construction (Design and Management) Regulations 2015 (CDM 2015), UKBP/TP137, UKBP/TP188 and UKBP/TP184.

Individuals who satisfy the requirements of this procedure and pass the assessment modules are TP141 Authorised or TP141 Assessed to work on National Grid assets only. Therefore these authorisations or assessments must not be used as confirmation of competency to work on any assets owned by other companies.

Roles requiring authorisation are:

Commissioning Authorisations

•Commissioning Panel Chairman

•Commissioning Officer

•Commissioning Engineer (National Grid) & (Supplier)

Settings Engineers Authorisations

•Settings Engineer (Assurance) & (Verification)

Design Assurance Authorisations

•P&C Design Engineer (Assurance)

•Substation HV Design Engineer (Assurance)

•Overhead Line Design Engineer (Assurance)

•HV Cable Design Engineer (Assurance)

•Substation Civil Design Engineer (Assurance)

•Roles requiring assessment are:

Contractor Design Approval Assessments

•Contractor Design Approval Engineer (P&C)

•Contractor Design Approval Engineer (Substation HV)

•Contractor Design Approval Engineer (Overhead Line)

•Contractor Design Approval Engineer (HV Cable)

•Contractor Design Approval Engineer (Substation Civil)

Principal Designer Assessments

•Principal Designer (Pre Contract)

•Principal Designer (Design & Build)

Note ! The appointed Principal Designer at the pre contract award stage shall be referenced as Principal Designer (Pre Contract).The appointed Principal Designer at the post contract award stage shall be referenced as Principal Designer (Design & Build).

It is recognised that for investments of medium and low complexity the full application of this Transmission Procedure (TP) may not provide the most cost efficient means of delivering that investment and hence TP governance options as per UKBP/TP500 Appendix A can be applied to this procedure.

TP governance options defined in UKBP/TP500 Appendix A include those that are already detailed in this Transmission Procedure and those that are additional and not detailed in this Transmission Procedure.

Amendments to this procedure shall be reflected in UKBP/TP500 Appendix A (if required) and may result in re-issue of UKBP/TP500 within the same period.


Edition : 10
File Size : 1 file , 510 KB
Number of Pages : 69
Published : 04/01/2015

History

NG UKBP/TP 141
Published Date: 04/01/2015
UK Business Procedure/Transmission Procedures - Authorisation Process for Commissioning, Settings and Design assurance Roles and Assessment Process for Contractor Design Approval Roles and Principal Designer Role
$275.7
NG UKBP/TP 141A
Published Date: 03/01/2009
UK Business Procedure/Transmission Procedures - Authorisation Process for Commissioning, Settings and Design Engineers
$55.2

Related products

NG TS 2.31
Published Date: 01/01/2011
Technical Specifications - High Voltage Direct Current (Hvdc) Converters
$138
NG SCT 53
Published Date: 05/01/2012
Site Commissioning Tests - Gas Insulated Transmission Line (GIL) Systems
$55.2
NG TGN(E) 255
Published Date: 06/01/2012
Technical Guidance Notes - Functional Requirements for GIS Local Control and Protection
$55.2
NG TGN(E) 214
Published Date: 12/01/2005
Technical Guidance Notes - Guidance for Fittings-Only Overhead Line Refurbishments
$55.2

Best-Selling Products

NAR CDG
Published Date:
Contest Directors Guide
$2.7
NAR CMASSPB
Published Date:
CMASS Plan Book
$3.6
NAR ED-12
Published Date:
Lower Tropospheric Probe
$1.2
NAR ED-20
Published Date:
Model Rocket Classroom Activities
$3
NAR ED-25
Published Date:
Rocketry Electrical Projects
$1.8
NAR GCCC
Published Date:
Guide to Competition for the Casual Competitor
$2.4