PURPOSE AND SCOPE
The purpose of this document is to define the responsibilities and tasks that comprise Core Construction Technical Assurance.
1. To both define/shape National Grid policy and process and audit/assist adherence to the same by the Alliances and Legacy Projects - with the objective of:
a) Targeting zero SHES incidents.
b) Targeting the very highest level of system reliability.
c) Enacting best and professional working practices
2. With reference to the Transmission Electricity Capital programme:
a) Agree the Capital programme for the next five years with Asset Management
b) Under the Project Manager (Core Construction Manager) for the NEC Contract Agreement – agree the content of the Capital programme to be delivered by each Alliance.
c) Manage the two-way change management process between Asset Management and the Alliances
3. To support the delivery of Legacy projects in achieving 1a), b) and c) above.
| Edition : | 2 |
| File Size : | 1 file , 100 KB |
| Number of Pages : | 18 |
| Published : | 05/01/2008 |